| Location | LAO PDR |
| Owner | GMS Lao Co., Ltd. |
| Employer | GMS Lao Co., Ltd. |
| Main Contractor | Right Tunnelling Co.,Ltd. |
| Contract Period | 2007 - 2008 |
| Percentage Completed | Finished |
| Role | Main Contractor |
| Project Detail | The Project is located in Lao PDR. The works under this Contract as belows : 1. Open Excavation & Slope Stabilization for Adit portal 2. Underground Excavation & Temporary Support Works : D-shaped, 2.5 x 3.0 m, Length 575.5 m 3. Geological Observation and report submission. |