Location | NAKORN-NAYOK, THAILAND |
Owner | Royal Irrigation Department |
Employer | Asdecon Corp. Ltd.-Team Consulting Engineers Co.,Ltd. and COYNE ET BELLIER |
Main Contractor | CCVK Joint Venture |
Contract Period | 2000 - 2003 |
Percentage Completed | Finished |
Role | Sub-contractor |
Project Detail |
Construction of Roller Compacted Concrete - RCC dam (Royal Development Project), the Project is located in Nakhon Nayok province. The works under this Contract as belows 1. Open Excavation Work - Rock Excavation (Control Drilling & Blasting) : 527,909 cu.m 2. Underground Excavation Works - Drainage Tunnel, total length : 1,480 m - D shaped, 2.5x3.0 m, (TBR-D1,TSL-D2, TSB-D1 and TSB-D3) - Grouting Tunnel, Horseshoe shaped, 3.0x2.7 m (TSB-PC) : 430 m 3. Tunnel Supports and Stabilization Works - Tunnel Concrete lining : 4,656 cu.m - Steel Rib Support : 9.31 ton - Fully Grout Anchor Bar : 4,666 m - Shotcrete : 379 cu.m - Wire Mesh : 4.52 ton - Soil Nail, DB 32 mm, L = 10 m : 352 pcs - Grouting : 74 ton |